UPS was scheduled to get two 747-400's from Cargolux in October 2009 when Cargolux got their 747-8's. No telling what the plan is now.

747-8 schedule undone by 787 crisis, management errors
By Stephen Trimble

Stretched thin on engineers by the 787 production crisis, overwhelmed by
unexpected design requirements and caught out by a supposedly mature supply
chain, Boeing marked the 747-8 family's third anniversary on 14 November by
announcing a stunning schedule delay.

Boeing shifted the delivery date for the 747-8 Freighter to Cargolux from
late 2009 to the third quarter of 2010. First delivery of the 747-8
Intercontinental, a passenger variant struggling to attract orders, dropped
from late 2010 to the second quarter of 2011.

Boeing's marketing material has already trimmed back performance comparisons
between the 747-8F and the Airbus A380.

Compared with a fact sheet dated 2005, Boeing's current online fact sheet
has reduced the 747-8F's fuel burn advantage to the A380 from 14% to 11%.
Boeing has also trimmed its projected advantage on fuel burn per ton from
25% to 24% and on ton mile costs from 23% to 22%.

With the 787-8 already 18 months behind schedule and facing new delays, the
747-8 family's setback may seem trivial. However, as a stretched and
rewinged extension of the 45-year-old 747 family, developing the 747-8 was
not expected to face nearly as many challenges as the all-new 787 production
system.

The news also marred an otherwise rare hopeful moment for Boeing Commercial
Airplanes this year.

On the same day Boeing disclosed the six- to nine-month delay for the
747-8F, the airframer signed a tentative agreement with the Society of
Professional Engineering Employees in Aerospace, relieving concerns about a
looming strike by 21,000 workers.

The news also came only five days after Boeing's 27,000 machinists returned
from a costly, two-month strike.

The absence of Boeing's production workforce in September and October is
partly to blame for the 747-8 delay. However, Boeing acknowledges the work
stoppage by the International Association of Machinists and Aerospace
Workers played only a bit-part in the story.

Indeed, Boeing executives now describe coming to grips with the scale of the
747-8's problems in August - shortly after the first 747-8F started final
assembly and just before the IAM strike began on 6 September.

The IAM strike began "shortly after we initiated a review of the [747-8]
program," Boeing vice-president Randy Tinseth wrote on his blog on 14
November.

Boeing launched the review to find out how far the programme had fallen
behind. Months earlier, Boeing had designated August as a critical month in
the 747-8F's development and, outwardly, events seemed in order. As
scheduled, the first airframe started final assembly and a far-flung team of
engineers managed to release 90% of the engineering drawings for the
aircraft.

In achieving both milestone events, however, Boeing was suddenly forced to
come to grips with supply-chain breakdowns that until then were recognised
but not understood, says Michael Teal, the 747's chief engineer: "After we
got to the 90% release milestone of engineering drawings in early third
quarter and started to begin production we realised we weren't getting the
parts in on time. A lot of [the issues] came home at that point."

To be sure, hints of internal issues had appeared before, even to outsiders.
Boeing reassigned the original programme manager, Dan Mooney, last
September, amid a broader upheaval caused by problems with the 787-8.

The management shakeup was quickly followed by a schedule reshuffling.
Boeing originally planned to assemble 747-8s and the 747-400s concurrently
on the same line.

This ambitious plan would save months on the schedule, but require
machinists and the supply chain to produce the older model at the same time
as they learned how to build the new aircraft. Complicating concerns about
the concurrency issue, Boeing also faced an unexpected problem with the
747-8 wing's new supercritical airfoil design, Teal says.

By September 2007, the concurrent production strategy was deemed too risky,
but executives refused to the delay the entry-into-service date. Instead,
Boeing decided to shift the schedule risk from the production line to the
flight-test phase.

The airframer moved back assembly of the first 747-8F to August, allowing a
clean break between the 747-400 and the new derivative. Boeing also
postponed the roll-out date from late 2008 to February 2009.

At the same time, Boeing decided to compress the flight-test schedule,
allowing the first 747-8F to be delivered on time despite the production
delay.

Unfortunately, that left a short flight-test period to certificate the
airworthiness of an aircraft stretched by 5.6m (18ft), which also features
an all-new advanced airfoil, all-new General Electric GEnx-2B67 engines and
new onboard systems derived from the 787.

"When we moved the line numbers last year, we didn't change the [entry into
service] date," Teal says. "That caused us to put a higher-risk flight-test
programme in place. We're adding that time back in because we haven't found
a credible way to reduce risk in the flight-test phase."

The flight-test phase is now allotted between seven and nine months to
complete, Teal says. By comparison, Boeing completed the flight-test
programme for the 777-200LR, a perhaps less ambitious derivative programme,
in about 10 months in 2005.
Roberto is offline  
Old 11-25-2008, 01:22 PM
  #2  
Gets Weekends Off
 
Sideshow Bob's Avatar
 
Joined APC: Oct 2006
Position: MD11 CPT
Posts: 1,077
Default

Originally Posted by Roberto View Post
UPS was scheduled to get two 747-400's from Cargolux in October 2009 when Cargolux got their 747-8's. No telling what the plan is now.

747-8 schedule undone by 787 crisis, management errors
By Stephen Trimble

Stretched thin on engineers by the 787 production crisis, overwhelmed by
unexpected design requirements and caught out by a supposedly mature supply
chain, Boeing marked the 747-8 family's third anniversary on 14 November by
announcing a stunning schedule delay.

Boeing shifted the delivery date for the 747-8 Freighter to Cargolux from
late 2009 to the third quarter of 2010. First delivery of the 747-8
Intercontinental, a passenger variant struggling to attract orders, dropped
from late 2010 to the second quarter of 2011.

Boeing's marketing material has already trimmed back performance comparisons
between the 747-8F and the Airbus A380.

Compared with a fact sheet dated 2005, Boeing's current online fact sheet
has reduced the 747-8F's fuel burn advantage to the A380 from 14% to 11%.
Boeing has also trimmed its projected advantage on fuel burn per ton from
25% to 24% and on ton mile costs from 23% to 22%.

With the 787-8 already 18 months behind schedule and facing new delays, the
747-8 family's setback may seem trivial. However, as a stretched and
rewinged extension of the 45-year-old 747 family, developing the 747-8 was
not expected to face nearly as many challenges as the all-new 787 production
system.

The news also marred an otherwise rare hopeful moment for Boeing Commercial
Airplanes this year.

On the same day Boeing disclosed the six- to nine-month delay for the
747-8F, the airframer signed a tentative agreement with the Society of
Professional Engineering Employees in Aerospace, relieving concerns about a
looming strike by 21,000 workers.

The news also came only five days after Boeing's 27,000 machinists returned
from a costly, two-month strike.

The absence of Boeing's production workforce in September and October is
partly to blame for the 747-8 delay. However, Boeing acknowledges the work
stoppage by the International Association of Machinists and Aerospace
Workers played only a bit-part in the story.

Indeed, Boeing executives now describe coming to grips with the scale of the
747-8's problems in August - shortly after the first 747-8F started final
assembly and just before the IAM strike began on 6 September.

The IAM strike began "shortly after we initiated a review of the [747-8]
program," Boeing vice-president Randy Tinseth wrote on his blog on 14
November.

Boeing launched the review to find out how far the programme had fallen
behind. Months earlier, Boeing had designated August as a critical month in
the 747-8F's development and, outwardly, events seemed in order. As
scheduled, the first airframe started final assembly and a far-flung team of
engineers managed to release 90% of the engineering drawings for the
aircraft.

In achieving both milestone events, however, Boeing was suddenly forced to
come to grips with supply-chain breakdowns that until then were recognised
but not understood, says Michael Teal, the 747's chief engineer: "After we
got to the 90% release milestone of engineering drawings in early third
quarter and started to begin production we realised we weren't getting the
parts in on time. A lot of [the issues] came home at that point."

To be sure, hints of internal issues had appeared before, even to outsiders.
Boeing reassigned the original programme manager, Dan Mooney, last
September, amid a broader upheaval caused by problems with the 787-8.

The management shakeup was quickly followed by a schedule reshuffling.
Boeing originally planned to assemble 747-8s and the 747-400s concurrently
on the same line.

This ambitious plan would save months on the schedule, but require
machinists and the supply chain to produce the older model at the same time
as they learned how to build the new aircraft. Complicating concerns about
the concurrency issue, Boeing also faced an unexpected problem with the
747-8 wing's new supercritical airfoil design, Teal says.

By September 2007, the concurrent production strategy was deemed too risky,
but executives refused to the delay the entry-into-service date. Instead,
Boeing decided to shift the schedule risk from the production line to the
flight-test phase.

The airframer moved back assembly of the first 747-8F to August, allowing a
clean break between the 747-400 and the new derivative. Boeing also
postponed the roll-out date from late 2008 to February 2009.

At the same time, Boeing decided to compress the flight-test schedule,
allowing the first 747-8F to be delivered on time despite the production
delay.

Unfortunately, that left a short flight-test period to certificate the
airworthiness of an aircraft stretched by 5.6m (18ft), which also features
an all-new advanced airfoil, all-new General Electric GEnx-2B67 engines and
new onboard systems derived from the 787.

"When we moved the line numbers last year, we didn't change the [entry into
service] date," Teal says. "That caused us to put a higher-risk flight-test
programme in place. We're adding that time back in because we haven't found
a credible way to reduce risk in the flight-test phase."

The flight-test phase is now allotted between seven and nine months to
complete, Teal says. By comparison, Boeing completed the flight-test
programme for the 777-200LR, a perhaps less ambitious derivative programme,
in about 10 months in 2005.
Question for us is what kind of contract was signed between UPS and Cargolux. If it had a specific date with no escape clauses, too bad for them. If it had the clauses (more likely) too bad for us. If they have to give the jets up and we don't really need them for the core business, how about we wet lease the planes AND IPA crews to them.

Problem is, more was known about the Soviet politburo than is known about UPS' dealings.
Sideshow Bob is offline  
Old 11-25-2008, 01:37 PM
  #3  
Gets Weekends Off
 
JustUnderPar's Avatar
 
Joined APC: Jun 2006
Position: UPS Captain
Posts: 837
Default

New 380 SDF bid?
JustUnderPar is offline  
Old 11-25-2008, 01:54 PM
  #4  
Gets Weekends Off
 
Joined APC: Jul 2008
Position: MD CA
Posts: 705
Default

According to some in ANC, mangt. types, the 747-400 will be based in SDF by next peak. Then ANC will be junior again!!!
Commando is offline  
Old 11-25-2008, 02:02 PM
  #5  
Gets Weekends Off
 
JustUnderPar's Avatar
 
Joined APC: Jun 2006
Position: UPS Captain
Posts: 837
Default

Originally Posted by Commando View Post
According to some in ANC, mangt. types, the 747-400 will be based in SDF by next peak. Then ANC will be junior again!!!
Two 400 domiciles? Where you gonna get the jets?
JustUnderPar is offline  
Old 11-25-2008, 02:42 PM
  #6  
Tri-tanic operator
 
CactusCrew's Avatar
 
Joined APC: Jul 2006
Position: Doggie
Posts: 2,382
Default

DC-8s return to international service !

CactusCrew is offline  
Old 11-25-2008, 04:10 PM
  #7  
Gets Weekends Off
 
Sideshow Bob's Avatar
 
Joined APC: Oct 2006
Position: MD11 CPT
Posts: 1,077
Default

Originally Posted by JustUnderPar View Post
Two 400 domiciles? Where you gonna get the jets?
Exactly...

They aren't getting anymore past the 13 already scheduled...ooops, make that 11 since we may not get the Cargolux planes at least until the end of the world is rescheduled.

As far as management generated rumors, after five airlines I have never seen a place as bad for rumors as this place. When I hear one it reminds me of Slim Pickins in Dr. Strangelove...

"Now I've been to one world fair, a picnic and a rodeo and that's the stupidest thing I've heard come over a set of earphones."
Sideshow Bob is offline  
Old 11-25-2008, 04:44 PM
  #8  
Gets Weekends Off
 
Joined APC: Jul 2008
Position: MD CA
Posts: 705
Default

Since we're increasing the eastbound flights to CGN and DXB, maybe it will happen. I hope so, since this will get some dead wood out my way.
Commando is offline  
Old 11-25-2008, 05:46 PM
  #9  
Gets Weekends Off
 
JustUnderPar's Avatar
 
Joined APC: Jun 2006
Position: UPS Captain
Posts: 837
Default

Originally Posted by Commando View Post
Since we're increasing the eastbound flights to CGN and DXB, maybe it will happen. I hope so, since this will get some dead wood out my way.
Maybe in a few years they will open the -400 SDF domicile. I did hear once they have 20 tail numbers, the rest would go to SDF. The eastbound loads are nothing compared to the stuff coming from the pac rim.

Maybe they will keep the classics around after peak? Though I dont know what inspections are coming due.

The 8's have some pretty heavy stuff coming up too?? I guess that is why they want to park them as well.

The rumor stuff here is entertaining. Some good imaginations at work.

I will have to break out that movie again.
JustUnderPar is offline  
Old 11-25-2008, 07:13 PM
  #10  
Gets Weekends Off
 
Trash Hauler 1's Avatar
 
Joined APC: Nov 2005
Posts: 325
Default

Originally Posted by Sideshow Bob View Post
Exactly...

They aren't getting anymore past the 13 already scheduled...ooops, make that 11 since we may not get the Cargolux planes at least until the end of the world is rescheduled.

As far as management generated rumors, after five airlines I have never seen a place as bad for rumors as this place. When I hear one it reminds me of Slim Pickins in Dr. Strangelove...

"Now I've been to one world fair, a picnic and a rodeo and that's the stupidest thing I've heard come over a set of earphones."
Actually, the most UPS-appropriate quote from that movie is, "Mr President, I smell a big, fat, Commie rat!", in the immortal words of General Buck Turgidson.

TH1
Trash Hauler 1 is offline  
Related Topics
Thread
Thread Starter
Forum
Replies
Last Post
vagabond
Cargo
1
11-17-2008 04:05 AM
⌐ AV8OR WANNABE
Cargo
11
11-07-2008 05:23 PM
FR8K9
Cargo
12
10-06-2008 05:02 AM
FlyAstarJets
Cargo
38
09-27-2008 10:45 PM

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On



Your Privacy Choices