Originally Posted by 69boeing View Post
Does anyone on here know if we are allowed to slide and/or expand the same vacation in two adjacent months?

I have vacation that spans the August and September bid periods. Am I allowed to slide and expand to the left during the August bid period processing and then a month later expand the same vacation to the right during September’s processing? This is obviously assuming I still had some credit hours left after August’s expansion.

Never had this scenario before and don’t want to learn the hard way.

Thx.

You can slide once. You can expand on either side, so yes, you can expand in August and September as long as you have vacation days in both months.