Originally Posted by
trigg41
Anyone want to guess what the VTO's will be? I guess they could be as low as 48. Right?
My Guess? Gotta be within 13 of the high line, right? So, 58+21 for MD Capts!
Section 25.D.2.e - Secondary lines shall be constructed to comply with the provisions of Section 25.D.1.b. through D.1.e. (above); provided, however, that a secondary line constructed as a reserve line shall comply with the provisions of Section 25.D.3. (below).
Sec 25.1.b - Regular lines shall be constructed with a maximum of 313 hours TAFB in a 4-week bid period, and 390 hours TAFB in a 5-week bid period. Regular lines will only be constructed with a maximum of 15 work days in a 4-week bid period and 19 work days in a 5-week bid period.
c - Regular lines in a 4-week bid period shall contain at least 1 block of 4 consecutive days off, 1 block of 3 consecutive days off and 1 block of 2 consecutive days off. Blocks of days off may be combined.
d - Regular lines in a 5-week bid period shall contain at least 1 block of 4 consecutive days off, 2 blocks of 3 consecutive days off and 1 block of 2 consecutive days off. Blocks of days off may be combined.
e - Regular lines shall be constructed so that the difference between the high BLG and low BLG in a bid period package shall not exceed 11 CH. At the beginning of the January, 2008 bid period, the line spread shall change to 13 CH.
Section 25.D.3.a - A reserve line consists entirely of R-days and days off.
In a 4-week bid period, a reserve line shall contain a maximum of 15 R-days. In a 5-week bid period, a reserve line shall contain a maximum of 19 R-days.
b - In the top 60% of reserve lines, R-days shall be grouped into a block(s) with a minimum of 4 R-days. Other reserve lines shall have block(s) with a minimum of 3 R-days; provided, however, that reserve lines that contain blocks of 3 R-days shall not contain any R-days on weekends.
c - A reserve line may be constructed with an additional R-day(s) that carries over into the following bid period.
d - There shall be a minimum of 10% R-24 lines per bid pack, with a minimum of 1 R-24 line (described in Section 25.M.2.). The Company and the SIG shall coordinate to establish a percentage of R-24 lines by bid pack, and this percentage shall be reevaluated on a quarterly basis.